Austria’s Ennstal line: renewing 29 kilometres of 220 kV high-voltage infrastructure
Powerlines Energy Austria is renewing 29 kilometres of 220 kV transmission infrastructure for Austrian Power Grid AG across two construction lots.Austria’s Ennstal line: renewing 29 kilometres of 220 kV high-voltage infrastructure
Powerlines Energy Austria is renewing 29 kilometres of 220 kV transmission infrastructure for Austrian Power Grid AG across two construction lots.
When Austrian Power Grid AG launched the renewal of the 220 kV Ennstal line between Wagrain and Weißenbach, Powerlines Energy Austria was appointed to deliver two construction lots covering around 29 kilometres of the line. Powerlines Energy Austria, an Equans entity, is responsible for two construction lots covering about 29 kilometres of the 73-kilometre Ennstal line.
The challenge
High-voltage transmission work on a live national grid leaves no room for improvisation. The Ennstal Line renewal involves two geographically separate construction lots, requiring coordinated planning between field teams and APG across different phases of the project. Every operation, from dismantling existing structures to installing and commissioning new pylons, must meet Austrian transmission network standards.
The solution
Powerlines Energy Austria is responsible for two construction lots covering about 29 kilometres of the 73-kilometre Ennstal line. Its scope includes:
- dismantling and rebuilding 95 pylons on the same sites;
- installing around 350 kilometres of conductors and 60 kilometres of earth wire.
Works are being carried out to the technical and safety standards required for 220 kV transmission infrastructure, with coordination between Powerlines teams and APG throughout the project.
Our value
- FOR GRID RELIABILITYRenewal of 220 kV transmission infrastructure as part of the modernisation of the Ennstal line.
- FOR SAFETYEvery phase is planned and carried out in line with the technical and safety requirements for 220 kV transmission infrastructure.
- FOR LONGEVITYNew pylon structures designed to serve the Austrian grid for the long term.